How do I track own production without using the Own Production module?

Let the budget drive the final forecast, correct continuously with expected additions, and split own production into phases on separate production codes.

If you don't use the Own Production module, you track own production directly on the production code. Don't add a contract on the code; let the budget from the estimate drive the final forecast, and correct along the way with expected additions based on what has been incurred.

How to do it

  1. Don't add a contract on production codes with own production. The budget then drives the final forecast.

  2. Keep an eye on the posted cost on the code, which comes automatically from the accounts.

  3. If you see that the code will end higher than the budget, add an expected addition on the code via Add → Expected Addition.

  4. Make sure costs are posted continuously to the correct production code in the accounts.

A production code opened from Prod. codes. 1: Budget for the production code. 2: Final forecast in the panel on the right. 3: the Add button, where you add an expected addition, uncertainty or purchase.

Tips for large projects

Split own production into several production codes by phase, for example foundation, building shell and interior fit-out. When a phase is finished, you know everything has been expensed on that code. You then have the actual result for the phase and can assess the rest more precisely, instead of one large lump item that is only settled when the project is finished.

When should I use the module instead?