If there is no Change Order Sub yet, click Link on the line in the Change Order Client and choose New cost. This creates a new Change Order Sub for the subcontractor or consultant directly from the change order. Enter the expected amount as the cost claim, and leave cost at 0 until it should go to the final forecast.
How to do it
Open the Change Order Client and go to the line.
Click Link on the left of the line.
Choose New cost. The New Change Order Sub window opens.
Fill in Number, Name, Group, Contract and Supplier.
Under Costs, enter the Cost claim with the expected amount. Cost can stay at 0.
Save.
Does the subcontractor change order already exist?
Instead, choose Pass on costs and select the existing Change Order Sub, for example a change notice from the consultant.
Good to know
If you don't know which number the subcontractor change order will get, enter a temporary number. Numbering is free and can be corrected later.
It is Cost that goes to the final forecast. Set it when you want the cost to count.