We recommend always turning on Forecast goes to the project forecast, so that Setup and Operation drives the final forecast. For calculating the final forecast, the most common and recommended choice is posted values for closed months plus accrued figures ahead. Consider using Unique production code for each expense item, so invoices can be routed automatically.
The settings
Forecast goes to the project forecast: The forecast from Setup and Operation goes to the final forecast on the production codes. We recommend always keeping this on.
Final forecast calculation: Three options:
posted values for closed months plus accrued ahead (recommended)
the budget always drives, regardless of invoices and accruals
the highest of budget and forecast, to be on the safe side
Unique production code for each expense item: Only the production codes are accrued, with one expense item per code.
Enable use of locked budget: You set an original budget per month, lock it and manage the forecast separately.
How to change the settings
Go to Setup and Operation.
Open Settings.
Choose the settings above and save.
Good to know
If you want to work with a locked budget, AIMZ is happy to offer a dedicated walkthrough. Contact us in the chat.