Setup and Operation

What Setup and Operation is, how expense items are accrued across months, and how deviations are handled.

Setup and Operation is the collective term for the costs you incur to establish, run and maintain the construction site itself — as opposed to the direct costs of the construction work, i.e. materials and labour hours on the permanent building elements.

Completed months show the actual posted cost, remaining months show the accrued plan

In practice, it is “the cost of being on site”: the infrastructure and administration needed to carry out the project, regardless of which specific building elements are being built.

These costs are usually separated into their own group of accounts or production codes (prod. codes), and typically make up 10–15% of the project’s total costs.

What is included

Setup — establishment

  • Site fencing, gates and securing the area

  • Site cabins — office and welfare cabins for the workforce

  • Cranes, hoists and scaffolding used across the whole site, not tied to one specific trade

  • Temporary roads, temporary power, water and drainage

  • Signage and logistics on site

Operation — ongoing

  • Site management and administrative staff

  • Cleaning and waste management

  • Power, heating and fuel during the construction period

  • Ongoing maintenance of the site setup

  • HSE costs

In short: Setup and Operation is the fixed overhead of running the construction site. It is charged over time, and it is directly sensitive to how long the project lasts.

Why it is followed up differently

Setup and Operation costs are generally not agreed fixed prices, as is often the case with contract work. They are based on consumption over time, and it is the project management itself that must control and follow up consumption on an ongoing basis.

Some costs are still fairly predictable because they are tied to fixed rental costs — for example renting site cabins. But even these depend directly on the final construction time: the longer the construction period, the longer the rental period and the higher the total cost.

Accrual and completing months

To control the costs, you distribute the budget across the months of the project period. This is what is called accrual.

The Setup and Operation module with the budget accrued across the months of the project period

Once a month has ended, you can choose to complete the month. The planned, accrued cost is then replaced by the actual cost incurred for the period.

Completing a month, where the accrued cost is replaced by the actual cost incurred

The Final Forecast is therefore calculated as a combination of:

  • Actual posted costs in completed periods

  • Planned, accrued costs in periods not yet completed

Expense items

Costs in Setup and Operation are created as expense items. Each account or prod. code can have one or more, depending on how detailed you want the follow-up to be. If you need to create many at once, see Create multiple expense items at once.

When creating one, you specify:

The dialog for creating a new expense item

  • Prod. code or account — which prod. code or account the expense item belongs to

    Selecting the production code or account for the expense item

  • Type — either Setup and Operation for general operating costs, or Staffing plan (a plan for staffing over time), where you manage staffing by adding multiple resources per expense item

    Selecting the expense item type: Setup and Operation or Staffing plan

  • Period — the time span the cost is distributed over. The project period is set by default, but can be adjusted

    Selecting the from and to period for the expense item

  • Name — AIMZ automatically gives the expense item the same name as the production code you select, but you can change it

    The name field for the expense item, prefilled with the production code name

  • Ledger accounts (optional) — which ledger accounts should be linked automatically to the expense item. See Automatic invoice matching with ledger accounts

    Selecting the ledger accounts to be linked automatically to the expense item

  • Cost distribution — the cost is distributed per month. You can choose to:

    • distribute the remaining budget evenly

    • distribute the existing budget evenly

    • use AI with text — for example, write «less at the start, and more towards the end»

    The cost distribution options: even distribution or AI distribution based on text

With the setting «Unique production code for each expense item», you can choose to follow up only one expense item per account or prod. code. This simplifies follow-up, since actual incurred costs can then be linked unambiguously to the right expense item — there is only one option to choose from. The setting is found under Settings in the top right of the Setup and Operation module.

Settings in the Setup and Operation module with the option for one expense item per production code

The Setup and Operation table with one expense item per production code

Budget and forecast per expense item

Each expense item has a budget that is held fixed. The accrued cost reflects this budget at project start, but can deviate as reality departs from what was originally planned.

The budget column for the expense items in Setup and Operation

Important: the budgets of all expense items under an account or prod. code should together match the budget for that account.

The budgets of several expense items summed up against the budget for the production code

Each expense item gets its own forecast. The sum of the forecasts for all expense items within one account is accumulated and affects the Final Forecast for the account — and therefore the project’s total Final Forecast.

The forecast per expense item summed up to the Final Forecast for the account

Note the terminology: we deliberately say «forecast», not «Final Forecast», when talking about a single expense item. This is to avoid confusion with the project’s overall Final Forecast.

Setting: what should drive the Final Forecast?

Under Settings in the top right of the Setup and Operation module, you can choose between two principles:

Settings in the Setup and Operation module for what should drive the Final Forecast

The choice between budget and forecast as the basis for the Final Forecast

1. Budget drives the Final Forecast. The Final Forecast is set equal to the original budget for the expense item, regardless of how the cost is actually distributed. Even if you adjust the distribution between months or complete months with deviations, the Final Forecast remains unchanged.

2. Forecast drives the Final Forecast — the default and recommended choice. The Final Forecast follows the forecast for the expense item, i.e. the combination of actual posted costs in completed periods and planned costs in the remaining ones. This gives a more dynamic, up-to-date picture as deviations arise.

This setting is essential to understand, because it determines whether the handling of deviations actually affects the Final Forecast, or whether the Final Forecast stays locked to the original budget.

Note: in the settings, the options may also be labelled «Forecast» and «Highest of budget and forecast». See What is the difference between «Forecast» and «Highest of budget and forecast» for accrued costs?

Rev. budget

Rev. budget = original budget + approved Change Order Client linked to the expense item. Change Order Client are changes towards the client that give the project additional income.

The revised budget column with approved Change Order Client linked to the expense item

A rev. budget means the project has more money to work with, because extra funds have been added on the income side. The rev. budget is adjusted only by the cost linked to the relevant Change Order Client — not by anything else.

Two deviation concepts

1. Deviation from rev. budget — the difference between the Final Forecast and the rev. budget.

  • Positive deviation: the Final Forecast is lower than the rev. budget. You are doing better than budgeted, and have money to spare.

  • Negative deviation: the Final Forecast is higher than the rev. budget. Less profit than originally assumed.

The column for deviation from revised budget

2. Deviation — the accumulated deviation between the accrued cost for a given month and what was actually posted, summed across all completed months.

The Deviation column with the accumulated deviation for completed months

If you cannot find these columns, you can make them visible by clicking Columns.

The Columns button above the table in Setup and Operation

The column selection where the deviation columns can be switched on

Handling deviations when completing a month

When you complete a month, there will almost always be a deviation. It is rare to plan the cost accrual for a month with complete accuracy.

You then need to decide how the deviation should be handled:

  • Approve the deviation — the Final Forecast changes in line with the difference between planned and actual cost incurred for the month. This requires the «Forecast drives the Final Forecast» setting to be selected.

  • Distribute the deviation onwards — if you want to smooth out the deviation so it does not directly affect the Final Forecast, it can be spread across upcoming months.

First, enter edit mode:

The Setup and Operation table in edit mode

Distribution can be done manually by entering figures directly in the table, or via predefined options:

  • Distribute to the next open month

  • Distribute to the last month

  • Distribute proportionally across upcoming months

  • Distribute evenly across upcoming months

The menu with options for distributing the deviation across upcoming months

Locked cost price estimate

Some companies want to manage Setup and Operation based on a locked cost price estimate, where the estimate is distributed over the project period once, locked, and all later adjustments are made in the Forecast column. The concept is optional and is activated under Settings in the module.

See the separate article for the full procedure: Locked cost price estimate in Setup and Operation.