No. A transaction moves budget between production codes. A production code can have several expense items in Setup and Operation, so AIMZ does not know which item should be changed. You therefore adjust the budget on the expense item yourself.
How to do it
Make the transaction on the production code as usual.
Go to Setup and Operation and find the relevant expense item, for example crane rental.
Open the expense item by clicking the name or the pencil on the row, and go to the Cost Price Estimate tab.
Click the icon to the right of Remaining rev. Cost Price Estimate and enter the change in the Adjustment rev. Cost Price Estimate field (at your company, "cost price estimate" may be called "budget").
Distribute the deviation across the months, and save.
Good to know
Be careful with the accrual in months that are already closed. Put the deviation in open months.
If the production code has only one expense item, it is easy to see where the change should go. If it has several, you must choose the right item.
The budget in Setup and Operation should match the revised budget on the production code.