The triple columns in Setup and Operation show planned and actual cost side by side, with the difference between them — either accumulated from project start up to today, or for a single month.
What the columns show
Each triple column consists of three figures:
Accrued — what you have planned for the period.
Posted — what has actually been posted in the same period.
Diff — the variance between the two.
This is what the triple columns look like:
Two variants
From start to current month — accumulated from project start up to the month you are in.
Current month — only the figures for that one month.
«Current month» means the month the columns are set to show. AIMZ selects this month automatically, but you can move it to an earlier month to see what the picture looked like then.
If you do not need all the columns at once, show — and hide — them under Columns. Keep the view as clean as possible.