Can a Change Order Client have lines on several production codes?

Yes. One Change Order Client can have several lines with different production codes. The production codes are not shown in the export to the client.

Yes. One Change Order Client can have several lines, and each line can have its own production code. The production codes are not shown in the export to the client.

How to do it

  1. Open the change order in Change Order Client.

  2. Click Add to add a line for each part of the change order.

  3. Select the right production code in the Production code column on each line.

  4. Save.

The Change Order Client table in AIMZ. 1 points to a change order that has lines on two production codes (6010 and 6060), and 2 to the Production code column, which shows all the production codes on each change order.

Good to know

  • This way, cost and income are distributed correctly across the production codes, even though the client only sees one change order.

  • Each line can be linked to one or more UE change orders.

  • You can add new lines even after the change order has been approved.