How do I link the accounting codes to a production code in AIMZ?

Enter the accounting codes in the field "System prod. codes for invoice integrations" under Advanced on the production code, and the invoices will be placed automatically.

You link the accounting codes to a production code in AIMZ under the Advanced tab on the production code. In the System prod. codes for invoice integrations field, enter the codes from the accounting system that should end up on this code. Invoices posted to these codes in the accounting system are then placed automatically on the production code in AIMZ.

How to do it

  1. Go to Prod. codes.

  2. Right-click the production code in the left margin and select Edit.

  3. Go to the Advanced tab.

  4. In the System prod. codes for invoice integrations field, type the code from the accounting system and press Enter. Repeat for more codes. You can also enter a range, for example 5000-5999.

  5. Save.

The window for a production code with the Advanced tab open. 1: the Advanced tab. 2: the System prod. codes for invoice integrations field, where you enter the accounting codes. 3: the help text about pressing Enter and entering ranges. 4: Save.

When is this useful?

  • When the codes in AIMZ have different numbers than in the accounting system, for example after you have introduced a new production code plan.

  • When several codes in the accounting system should be collected on one code in AIMZ, for example the whole payroll series.

Limitation

If the structure in AIMZ is more detailed than in the accounting system, for example two production codes in AIMZ against one in the accounting system, AIMZ does not know which code the invoice should go to. The invoices are then placed on one code and must be distributed manually. An alternative is to add an extra dimension in the accounting system where each invoice is tagged with the project-specific code.

Related questions