The change management system only captures what comes as a subcontractor change. Your own costs, such as provisions in setup and operation and own production, you must enter yourself as an expected addition in AIMZ.
How to do it
Go through the changes to the client and see whether they have own costs that do not come from subcontractors.
Go to Expected Addition and click + Expected Addition, or open the production code the cost belongs to and use the Expected Addition tab.
Select the production code, enter the amount in Cost and write in Description which change to the client the cost belongs to.
Click Confirm.
Good to know
A Change Order Client can be sent without the corresponding own cost being entered. Keep an eye on this.
If the own cost is missing, the final forecast becomes too low and the contribution margin too high.
When the actual cost arrives, you clean up the expected additions.