When the UE changes come from an external change management system, you make the change there. AIMZ only reads the UE claim from the change management system, so that is where the claim must be zeroed out or rejected.
How to do it
Go to the change management system and find the UE change.
Zero out or reject the claim there.
Go to Change Order Subcontractor in AIMZ. The update arrives and awaits approval.
Check the amount and approve the update.
Good to know
What AIMZ fetches from the change management system is the UE claim. The revenue side, that is, what is sent on to the client, you handle in AIMZ.
If the UE change has already been carried forward to a Change Order Client, you must also review the revenue there.
Updates from the change management system do not affect the final forecast until you have approved them.